Al Sagar Mall project features a four-level design encompassing a total area of 9,975 m², entirely covered by a steel structure. The layout includes:
- Basement Floor: Designed for parking, storage spaces, and mechanical rooms.
- Ground and Mezzanine Floors: Intended for retail shops, restaurants, gym, and office spaces.
- Roof Floor: An open area designated for outdoor mechanical equipment, gas rooms, and related utilities, also covered by the steel structure.
Commence date: December, 1st .2024
Completion date: July, 23, 2026
Project duration: 600 days
Original Contract Value: KD 8,430,000.000
Contract Value with approved VO’S : KD 11,198,649.250