Owner : Al Mulla Group (Al Mulla Automobiles CO.) Location : Shuwaikh, Kuwait Project Duration : 214 Days Contract Value : 4,120,000.000 KD Construction Handing Over and Maintenance of Mercedes Bridge Facility
Owner : KNCC Location : South Sabahiya Project Duration : 900 Days Contract Value : 42,000,000 KD Kuwait National Cinema Company has tendered Kuwait Mall Project, located in South Sabahiya on Plot 49 (79,640 sqm). The project consists of a Mall with External Plaza having a total built-up area of… read more →
Owner: AJIAL Real Estate and Entertainment Co. Project Commencement Date: 23 Jun. 2109 Contract Original Duration: 780 Days, Expected Finish Date: 10 Aug 2021 Project Value: 18,650,000 KWD The project contains 11 Cinemas, Public Areas, Restaurants, 6 Floors as Clinics, Each Floor Contain 8 Clinics and 9 Floors as Offices,… read more →
Owner : Jazeera Airways Project Duration : 365 Calendar days. Contract Value : 8,150,000.000 KD The project consists of establishing, executing, and handing over of Jazeera Airways Terminal & Car Park (with total plot area 8330 m2) which consists of: 1- Jazeera Terminal Building: is located on an area of about… read more →
Owner : Kuwait Danish Diary (KDD), it is built on around 6000m3 comprising One Basement, Ground, Mezzanine, Roof and Upper Roof Floor. Project Commencement Date: 1st December 2014, Contract Original Duration: 450 Days, Expected Finish Date: 23rd February 2016, Budget total price: 6,800,000 KWD
Owner : Bader Al Mulla & Brothers Location : Al-Rai 4th ring road Project Duration : 17 months Contract Value : 5,000,000 KD The project consists of a hall showroom for ACURA new brand starts in Kuwait, the building have two basements for parking and workshops in addition to the hall… read more →
Owner : Yossef Ahmed Al ghanim And Sons Location : Al-Rai 4th ring road Project Duration : 12 months Contract Value : 1,300,000 KD The project consists of a hall showroom for HONDA, the building have two basements for parking and workshops in addaition to the hall in ground floor and… read more →
Owner : M.S. Fajer Al-Sabah Al Ahliyh School Location : Salmiya, Kuwait Project Duration : 540 Days Contract Value : 3,560,000 KD Construction Handing Over and Maintenance of Fajer Al-Sabah Private School at Salmiya
Owner : Gulf Development House Location : Salmiya Original Project Duration : 24 months Contract Value : 15,000,000KD The project consists of a main building and a residential building. The main building have three basements and podium in ground to 4th floor in addition to Guest rooms in floors… read more →